Puterawardhana, Sjahihza and Ir. M. Taufik Hidayat, MT. and Dr. Eng. Ir. Ming Narto Wijaya, ST., MT., M.Sc. sc. (2021) Studi Alternatif Perencanaan Gedung RSUD dr. Soewandhi Surabaya pada Struktur Sambungan Balok-Kolom Menggunakan Sistem Beton Pracetak (Precast). Sarjana thesis, Universitas Brawijaya.

Abstract

Perencanaan kotruksi juga memerlukan inovasi dalam hal pengerjaan yang dapat mempercepat waktu pelaksanaan pengerjaannya.Gedung RSUD dr. Mohamad Soewandhi Surabaya ini dibangun menggunakan struktur beton bertulang yang kebanyakan kontraktor Indonesia berpendapat bahwa proses pengerjaan yang mudah dan telah diterapkan pada mayoritas bangunan di Indonesia. pekerjaan struktur menggunakan beton bertulang secara menyeluruh sebagai struktur utama juga memerlukan waktu yang cukup lama karena proses mengeringnya beton itu sendiri. Pertanyaan diatas mendorong penulis untuk menggunakan metode precast atau beton pracetak untuk melakukan penelitian alternatif tentang perencanaan Gedung RSUD dr. Mohamad Soewandhi Surabaya.Metode beton pracetak adalah teknologi kontruksi struktur beton dengan komponen-komponen yang dicetak terlebih dahulu pada suatu tempat khusus untuk mencetak beton tersebut (fabrication) dan selanjutnya dipasang langsung di lokasi proyek. Tujuan dari penelitian ini adalah untuk mengetahui cara pengangkatan pada elemen beton pracetak. mengetahui desain sambungan pada balok-kolom menggunakan sistem pracetak, serta mengetahui kekuatan sambungan pada balok-kolom menggunakan sistem pracetak pada Gedung RSUD dr. Mohamad Soewandhi Surabaya Berdasarkan hasil analisis perencanaan pada balok-kolom menggunakan sistem pracetak sebelum cor penuh dengan beban yang dipikul oleh balok tersebut merupakan beban sendiri dari balok. Saat pengangkatan balok menunjukkan bahwa jarak tumpuan saat pengangkatan sejauh 1,85 m dari tepi balok. balok induk pracetak yang berukuran 40/40 dengan tulangan lentur yang mengalami tarik yaitu 6-D25 dan tulangan yang mengalami tekan yaitu 3-D25 serta sengkang ø8-200 menghasilkan momen tumpuan yang besarnya sama dengan momen lapangan sebesar 830,955 kgm. Serta analisis hubungan balok –kolom pracetak baik yang ditengah maupun di pinggir struktur yang dilakukan pada kondisi setelah cor penuh dengan beban yang dipikul merupakan beban mati (D), beban hidup (L) dan beban gempa menunjukkan hasil yang aman terhadap lentur dan geser. Hal ini dapat dibuktikan dengan hasil analisis kapasitas momen di daerah tengah bentang menunjukkan momen nominal sebesar 499,294 kNm dimana lebih besar dari momen ultimate yang terjadi yaitu sebesar 392,192 kNm dan kuat geser nominal sebesar 3992,89 kN dimana lebih besar dari gaya geser yang terjadi yaitu sebesar 3981,5094 kN, sedangkan hasil analisis sambungan di daerah pinggir bentang menunjukkan momen nominal sebesar 687,56 kNm dimana lebih besar dari momen ultimate yang terjadi yaitu sebesar 132,545 kNm dan kuat geser nominal sebesar 2950,51 kN dimana lebih besar dari gaya geser yang terjadi yaitu sebesar 1810,7275 kN kN

English Abstract

Construction planning also requires innovation in terms of workmanship that can speed up the execution time of the work. RSUD dr. Mohamad Soewandhi Surabaya was built using a reinforced concrete structure which most Indonesian contractors think that the process is easy and has been applied to the majority of buildings in Indonesia. Structural work using reinforced concrete as a whole as the main structure also takes a long time because the concrete drying process itself. The above questions encourage the author to use the precast or precast concrete method to conduct alternative research on the planning of the RSUD dr. Mohamad Soewandhi Surabaya. The precast concrete method is a technology for the construction of concrete structures with components that are first printed in a special place to print the concrete (fabrication) and then installed directly at the project site. The purpose of this study was to determine how to lift the precast concrete elements. knowing the connection design on the beam-column using a precast system, and knowing the strength of the connection on the beam-column using a precast system at the RSUD dr. Mohamad Soewandhi Surabaya Based on the results of the planning analysis on the beam-column using a precast system before being cast, the load carried by the beam is the beam itself. When lifting the beam, it shows that the distance of support when lifting is 1.85 m from the edge of the beam. precast main beam measuring 40/40 with flexural reinforcement experiencing tension, namely 6-D25 and reinforcement in compression, namely 3-D25 and stirrups 8- 200 producing a bearing moment of the same magnitude as the field moment of 830,955 kgm. As well as the analysis of the relationship between precast beams and columns, both in the middle and at the edges of the structure, which was carried out in conditions after the casting was full with the dead loads (D), live loads (L) and earthquake loads showing safe results against bending and shearing. This can be proven by the results of the moment capacity analysis in the mid-span area showing a nominal moment of 499.294 kNm which is greater than the ultimate moment that occurs which is 392.192 kNm and a nominal shear strength of 3992.89 kN which is greater than the shear force that occurs, which is equal to 3981.5094 kN, while the results of the analysis of the connection at the edge of the span show a nominal moment of 687.56 kNm which is greater than the ultimate moment that occurs which is 132.545 kNm and nominal shear strength of 2950.51 kN which is greater than the shear force that occurs that is equal to 1810.7275 kN kN

Other obstract

-

Item Type: Thesis (Sarjana)
Identification Number: 0521070268
Uncontrolled Keywords: Kata Kunci : Profil, Perencanaan, Pracetak, Beton, Perkuatan
Subjects: 600 Technology (Applied sciences) > 624 Civil engineering
Divisions: Fakultas Teknik > Teknik Sipil
Depositing User: yulia Chasanah
Date Deposited: 11 Feb 2022 07:05
Last Modified: 30 Sep 2024 01:39
URI: http://repository.ub.ac.id/id/eprint/189723
[thumbnail of -Sjahihza Putera Wardhana.pdf] Text
-Sjahihza Putera Wardhana.pdf

Download (4MB)

Actions (login required)

View Item View Item