Studi Perencanaan Penyediaan Air Bersih Pada Gedung Baru Teknik Pengairan Universitas Brawijaya

Rifki, MIkhsan (2017) Studi Perencanaan Penyediaan Air Bersih Pada Gedung Baru Teknik Pengairan Universitas Brawijaya. Sarjana thesis, Universitas Brawijaya.

Abstract

Perkembangan Jurusan Teknik Pengairan Universitas Brawijaya dari tahun ke tahun semakin meningkat. Dengan melihat tantangan perkembangan pendidikan tinggi dimasa mendatang yang semakin ketat sejalan dengan pesatnya ilmu pengetahuan dan teknologi. Tuntutan terhadap kualitas sumber daya manusia menjadi lebih kompetitif mengharuskan sumber daya manusia yang dihasilkan oleh perguruan tinggi menjadi lebih berkualitas. Dari sisi pelayanan pendidikan penyediaan fasilitas gedung dan sarana perkuliahan merupakan penunjang kelancaran proses belajar mengajar. Hal tersebut menjadikan alasan dibangunnya Gedung Baru Jurusan Teknik Pengairan Universitas Brawijaya. Dalam pembangunan sebuah gedung diperlukan suatu sistem pendistribusian air bersih untuk memenuhi kebutuhan air bersih bagi semua orang yang melakukan aktivitas pada gedung tersebut. Dalam pemanfaatan air diperlukan pengaturan yang cermat agar diperoleh hasil yang maksimum dan air terdistribusi sesuai dengan kebutuhan. Kebutuhan air dihitung berdasarkan jumlah penghuni dan berdasarkan jenis dan jumlah alat plambing. Dari kedua metode tersebut didapat kan hasil rata-rata kebutuhan air bersih adalah 76.200 liter/hari. Sistem pendistribusian yang digunakan pada gedung adalah sistem tangki atap dengan watu pemakaian gedung dari pukul 07:30 sampai pukul 18:00. Air bersih yang didapat dari jaringan PDAM terdekat di tampung sementara di Ground Resevoir dengan ukuran 8 m3 sebelum di pompa menggunakan pompa dengan kapasitas 10,5 liter/detik dan head pompa 50 m menuju tangki air atas (roof tank) kapasitas 12,5 m3 dengan lama pemompaan dari pukul 07:00 sampai pukul 17:00. Setelah ditampung air bersih di distribusikan ke jaringan pipa menuju alat saniter pada masing-masing lantai sesuai dengan letaknya. Pipa yang digunakan adalah pipa PVC dengan diameter 2 inch, 1,5 inch, 1,25 inch, 1 inch, 0,75 inch, dan 0,5 inc sedangkan untuk pipa dari Ground Resevoir menuju roof tank dan pipa vertikal digunakan pipa Galvanized Iron ukuran 3 inch. Dari hasil simulasi menggunakan software waterCAD V8i didapatkan kecepatan rata-rata pada pipa jaringan distribusi air bersih sebesar 1,203 m/detik sedangkan untuk kehilangan tinggi rata-rata pipa sebesar 0,127 m dan rata-rata tekanan yang terjadi pada setiap junction adalah sebesar 1,05 kg/cm2. Biaya yang dibutuhkan untuk pengadaan bahan jaringan distribusi air bersih pada Gedung Baru Teknik Pengairan Universitas Brawijaya meliputi pengadaan alat saniter, pengadaan pipa, pengadaan aksesoris pipa, pengadaan Roof Tank, Pengadaan Ground Reservoir, dan pengadaan Pompa sebesar Rp. 204.668.051,00.

English Abstract

Department of Water Resources Engineering in Brawijaya University had grown in faster rate. New facilities, including building and lecture class, must be added and provided to support the learning and teaching activities. It was the reason why new building must be constructed in the realm of Water Resources Engineering Department in Brawijaya University. The development of a building always needed a clean water distribution system to meet the demand for clean water of everyone who conducted the activity inside the building. The demand of clean water at the new building of Water Resources Engineering reached 76.200 m3/day while the demand of water for fire extinguishing network was 75.294 m3. Distribution system in the building was using roof tank system. Building usage was arranged from 8 am to 6 pm. Base water was obtained from nearby PDAM network. The water was temporarily retained into ground reservoir at 8 m3 capacity before it was pumped using 10.5 liters/second capacity pump with 50 m pump head, toward upper water tank (roof tank). Roof tank had a capacity of 25 m3 and it received the pump release from 7 am to 5 pm. The retained clean water was distributed through pipe network toward sanitary devices at certain places in each floor. The type of the pipe was PVC at diameter 2 inches, 1.5 inches, 1.25 inches, 1 inches, 0.75 inches, and 0.5 inches. Pipes from Ground Reservoir were set toward roof tank. Vertical pipe was using Galvanized Iron Pipe at 3 inches size. Fire extinguishing network system was applying sprinkle system. The capacity of ground reservoir was 75 m3, while roof tank capacity was 10 m3. The capacity of the pump was 20 liters/second with pump head of 55 m. The simulation using software WaterCad V8i had produced some results. For clean water distribution network, water pressure reached 0.418-1.49 kg/cm2 whereas the water speed attained 0.92-2.91 m/second. For fire extinguishing network, water pressure attained a rate of 0.49-2.48 kg/cm2 while water speed reached the rate of 0.15-2 m/second. All these results conformed to the requirement of planning. Cost budget for planning both clean water distribution network and fire extinguishing network would be Rp. 390,000,000.00.

Item Type: Thesis (Sarjana)
Identification Number: SKR/FT/2017/74/051701227
Subjects: 600 Technology (Applied sciences) > 627 Hydraulic engineering > 627.5 Reclamations, Irrigation, related topics > 627.52 Irrigation
Divisions: Fakultas Teknik > Teknik Pengairan
Depositing User: Sugiantoro
Date Deposited: 27 Feb 2017 14:12
Last Modified: 24 Oct 2021 10:21
URI: http://repository.ub.ac.id/id/eprint/145626
[thumbnail of 2._Lembar_Pengesahan.pdf]
Preview
Text
2._Lembar_Pengesahan.pdf

Download (1MB) | Preview
[thumbnail of 6._Daftar_Isi.pdf]
Preview
Text
6._Daftar_Isi.pdf

Download (1MB) | Preview
[thumbnail of 8._Bab_I_(Pendahuluan).pdf]
Preview
Text
8._Bab_I_(Pendahuluan).pdf

Download (1MB) | Preview
[thumbnail of 10._Bab_III_(Metodologi_Studi).pdf]
Preview
Text
10._Bab_III_(Metodologi_Studi).pdf

Download (2MB) | Preview
[thumbnail of 9._Bab_II_(Tinjauan_Pustaka).pdf]
Preview
Text
9._Bab_II_(Tinjauan_Pustaka).pdf

Download (3MB) | Preview
[thumbnail of 4._Ringkasan.pdf]
Preview
Text
4._Ringkasan.pdf

Download (1MB) | Preview
[thumbnail of 11._Bab_IV_(Pembahasan).pdf]
Preview
Text
11._Bab_IV_(Pembahasan).pdf

Download (3MB) | Preview
[thumbnail of 13._Daftar_Pustaka.pdf]
Preview
Text
13._Daftar_Pustaka.pdf

Download (1MB) | Preview
[thumbnail of 12._Bab_V_(Penutup).pdf]
Preview
Text
12._Bab_V_(Penutup).pdf

Download (1MB) | Preview
[thumbnail of 14._Lampiran_1_(Penentuan_Diameter_Pipa_Air_Bersih).pdf]
Preview
Text
14._Lampiran_1_(Penentuan_Diameter_Pipa_Air_Bersih).pdf

Download (3MB) | Preview
[thumbnail of 15._Lampiran_2_(Kondisi_Pipa_Distribusi).pdf]
Preview
Text
15._Lampiran_2_(Kondisi_Pipa_Distribusi).pdf

Download (2MB) | Preview
[thumbnail of 16._Lampiran_3_(Kondisi_Junction).pdf]
Preview
Text
16._Lampiran_3_(Kondisi_Junction).pdf

Download (2MB) | Preview

Actions (login required)

View Item View Item