Abstract

PT. Nusa Indah Metalindo adalah perusahaan manufaktur baja ringan di Driyorejo, Gresik yang memproduksi berbagai profil baja. Produk terbanyak yang dihasilkan adalah Kanal C 75 dengan output 480.213 batang pada periode Oktober 2024–September 2025, namun target bulanan 45.000 batang kerap tidak tercapai. Penyebab utamanya adalah tingginya unplanned downtime pada mesin Roll Forming yang merupakan satu-satunya mesin produksi Kanal C 75, dengan rata-rata downtime sebesar 609 menit/bulan, jauh melampaui batas toleransi perusahaan sebesar 300 menit/bulan. Penelitian ini bertujuan mengukur efektivitas mesin menggunakan OEE, mengidentifikasi kerugian dominan melalui Six Big Losses, serta menganalisis kegagalan kritis menggunakan Machinery Failure Mode and Effect Analysis (MFMEA). Hasil perhitungan OEE menunjukkan rata-rata nilai efektivitas mesin sebesar 69,18%, di bawah standar JIPM sebesar 85%. Nilai OEE tertinggi terjadi pada April 2025 (72,55%) dan terendah pada September 2025 (65,15%). Dari tiga komponen penyusun OEE, nilai availability rate rata-rata sebesar 93,74% telah memenuhi standar JIPM (>90%), dan quality rate rata-rata sebesar 99,19% juga melampaui standar JIPM (>99%). Namun, nilai performance rate rata-rata hanya 74,41%, jauh di bawah standar 95%, menjadikannya faktor utama rendahnya OEE. Analisis Six Big Losses mengidentifikasi tiga kerugian dominan: (1) Reduced Speed Losses sebesar 43,50% (27.541 menit), (2) Set Up and Adjustment Losses sebesar 28,84% (18.257 menit), dan (3) Idling and Minor Stoppage Losses sebesar 15,09% (9.551 menit). Akumulasi ketiganya mencapai lebih dari 87% dari total kerugian waktu produksi. Analisis MFMEA menghasilkan nilai kritis RPN sebesar 162,19, dengan 7 mode kegagalan prioritas: kebocoran dan pecahnya tabung pompa hidrolis (RPN tertinggi 294), pisau tumpul, kebocoran oli gearbox, patah dan aus pada roll disc (RPN 252), serta bearing macet/aus. Berdasarkan hasil tersebut, dirumuskan empat rekomendasi perbaikan: (1) penjadwalan planned maintenance berbasis MTBF untuk komponen kritis; (2) penerapan sistem Dual Head Uncoiler untuk menekan nilai set up dan idling losses; (3) penggunaan alat bantu feeler gauge untuk menurunkan nilai set up dan adjustment losses; serta (4) pembuatan checklist preventive maintenance terstruktur agar pengecekan komponen dapat dilakukan secara sistematis dan menyeluruh.

English Abstract

PT. Nusa Indah Metalindo is a lightweight steel manufacturing company in Driyorejo, Gresik, producing various steel profiles. The highest-volume product, Kanal C-75, reached 480,213 bars during October 2024–September 2025, yet the monthly target of 45,000 bars was consistently missed. The primary cause is excessive unplanned downtime on the Roll Forming machine the sole machine in Kanal C-75 production averaging 609 minutes/month, far exceeding the company's 300-minute tolerance. This study aims to measure machine effectiveness using OEE, identify dominant losses through Six Big Losses, and analyze critical failures using Machinery Failure Mode and Effect Analysis (MFMEA). OEE calculations show an average effectiveness of 69.18%, below the JIPM standard of 85%. The highest OEE was in April 2025 (72.55%) and the lowest in September 2025 (65.15%). Among the three OEE components, availability rate averaged 93.74% (meeting JIPM's >90% standard) and quality rate averaged 99.19% (exceeding JIPM's >99% standard). However, performance rate averaged only 74.41%, far below the 95% standard, making it the primary driver of low OEE. Six Big Losses analysis identified three dominant losses: (1) Reduced Speed Losses at 43.50% (27,541 minutes), (2) Set Up and Adjustment Losses at 28.84% (18,257 minutes), and (3) Idling and Minor Stoppage Losses at 15.09% (9,551 minutes). Combined, these three losses account for over 87% of total production time lost. MFMEA analysis yielded a critical RPN threshold of 162.19, with 7 priority failure modes: hydraulic pump fluid leakage and tank rupture (highest RPN of 294), blade dulling, gearbox oil leakage, roll disc shaft fracture and surface wear (RPN 252), and bearing seizure/wear. Three improvement recommendations were proposed: (1) a planned maintenance schedule based on MTBF calculations for critical components; (2) implementation of a Dual Head Uncoiler system to reduce set up and idling losses; (3) The Use of Feeler Gauge as a Supporting Tool to Reduce Set Up and Adjustment Losses; and (4) structured preventive maintenance checklist to ensure systematic and complete machine inspection.

Item Type: Thesis (Sarjana)
Identification Number: 052607
Uncontrolled Keywords: Overall Equipment Effectiveness (OEE), Six Big Losses, Machinery Failure Mode and Effect Analysis (MFMEA), Mesin Roll Forming
Subjects: 600 Technology (Applied sciences) > 670 Manufacturing
Divisions: Fakultas Teknik > Teknik Industri
Depositing User: Unnamed user with username TI08
Date Deposited: 09 Oct 2026 02:09
Last Modified: 09 Oct 2026 02:15
URI: http://repository.ub.ac.id/id/eprint/260121
[thumbnail of DALAM MASA EMBARGO] Text (DALAM MASA EMBARGO)
-Muhammad Daffariiq Hauzaan Irfan.pdf
Restricted to Registered users only

Download (4MB)

Actions (login required)

View Item View Item