Salah satu komponen penting dalam sistem tenaga listrik adalah sistem proteksi yang dapat mengamankan dan meningkatkan keandalan sistem proteksi. Pada unit pembangkit listrik tentunya sering terjadi gangguan dari dalam maupun luar sistem yang dapat merusak peralatan-peralatan pembangkit. Oleh karena itu Unit Pembangkitan Gresik memiliki beberapa teknologi dalam sistem proteksi yang dapat menunjang produksi listrik yang terjamin. Salah satu permasalahan yang terjadi terletak pada unit PLTGU PT. Pembangkit Jawa Bali Unit Pembangkitan Gresik, dimana beberapa rele yang terpasang pada bus 6 kV beroperasi secara abnormal. Hal itu terjadi sebanyak 1-2 kali, namun ketika dilakukan uji coba terhadap rele tersebut tidak ada bagian yang rusak. Penelitian yang dilakukan di PT.PJB UP. Gresik bertujuan untuk mengganti rele yang lama dan melakukan penyetelan ulang rele. Rele yang diganti yaitu rele arus lebih, rele tegangan kurang dan rele sinkronisasi. Dari hasil penelitian ini, didapatkan bahwa setelan rele yang baru berbeda dengan setelan rele yang lama. Pada analisis setelan rele yang baru didapatkan setelan rele lebih sensitif terhadap gangguan yang terjadi yaitu arus setelan sebesar 876,456 A dengan time dial 0,14 untuk OCR dan 100 A dengan delay 0,26 detik untuk GFR. Sedangkan setelan rele tegangan kurang yang baru sama dengan setelan rele yang lama dan untuk setelan rele sinkronisasi yang baru terjadi perbedaan pada setelan ΔV yaitu nilai setelan yang baru sebesar 458,18 volt. Dari hasil analisis koordinasi rele setelan baru dengan rele yang terpasang pada pembebanan bus menunjukkan koordinasi rele sudah tepat dan urutan kerja rele sudah benar.

English Abstract

One of important component in electrical power system is protection system that can preserve and increase reability of system. In the power plant unit, often occurs interference from inside and outside system that can damage the generating equipment. Therefore, PT.PJB UP Gresik has some technology in protection system that can support the production of electricity. The problems that happened in unit of PLTGU PT. PJB UP Gresik, there are some existing relays on 6 kV bus operate abnormally. It happened 1 until 2 times, but when tested on the relays there was not damaged parts. The research done at PT. PJB UP. Gresik has two main purposes which are replacing the old relays and resetting relays. Replacement of relays are include overcurrent relay, undervoltage relay and synchronization relay. The results from this research show that new setting relays are different with old setting relays. Also, after analysing new setting relays more sensitive than old setting relays from short-circuit that was 876,456 A with time dial 0,14 for OCR and 100 A with delay 0,26 second for GFR. While the new setting undervoltage relay is the same with the old setting and new setting synchronization relay there is different setting for ΔV that was 458,18 volt. The results from new relays coordination analysis with existing relays on bus 6 kV show that relays coordination and the sequence of working relays are correct.

Item Type: Thesis (Sarjana)
Identification Number: SKR/FT/2017/963/051708806
Uncontrolled Keywords: rele arus lebih, rele tegangan kurang, rele sinkronisasi, setelan rele
Subjects: 600 Technology (Applied sciences) > 621 Applied physics > 621.3 Electrical, magnetic, optical, communications, computer engineering; electronics, lighting > 621.31 Generations, modification, storage, transmission of electric power > 621.317 Control devices
Divisions: Fakultas Teknik > Teknik Elektro
Depositing User: Budi Wahyono Wahyono
Date Deposited: 28 Sep 2017 01:54
Last Modified: 25 Nov 2020 09:12
URI: http://repository.ub.ac.id/id/eprint/2943
[thumbnail of Eka Citra Agustini.pdf]
Preview
Text
Eka Citra Agustini.pdf

Download (3MB) | Preview

Actions (login required)

View Item View Item